At the July 11th Town Board Meeting, The Huntington Town Board approved a Phase Two feasibility study towards the construction of a 528-space parking structure in Huntington Village.  The Board approved to extend the contract with Level G Associates of Old Bethpage, who also performed the Phase One feasibility study.  

Phase One of the study consisted of Level G studying the economic and physical feasibility of the parking deck, which would reside between New Street and Green Street in Huntington Village.

In Phase Two, Level G plans to reaffirm their preliminary conclusions by finalizing earlier estimates and projections while also including construction, financial, and revenue plans for the structure.  The final report will be submitted to key stakeholders involved in the project funding.  The $12,700 cost of Phase Two will be partially funded by the Town’s Economic Development Corporation.