4th Level Parking Spaces at South Parking Garage Re-Open April 8th

Spaces on the fourth level of the South Parking Garage at the Huntington train station, closed earlier this year as part an emergency repair project on the fifth level, are scheduled to reopen Wednesday, April 8.

The 116 fourth level stalls were closed as a safety precaution because they were situated directly beneath the fifth-level work, which included removing parking deck concrete in certain areas, repairing some post-tensioned cables and installing a new, epoxy-coated welded wire steel fabric for reinforcement. The project has reached a stage where the remaining work no longer presents a potential falling debris hazard to persons and vehicles on the fourth level, allowing for the spaces to reopen.

The 112 fifth-level stalls will remain closed during the required 20-day concrete curing period prior to caulking. They are now scheduled to reopen on April 20.